
December
2, 2011 - The ELS Center continues to progress towards
completion. The exterior drives and walks are near completion. Interior
finishes continue with flooring, ceilings, and cabinet installation. Electrical
is trimming outlets and switches; mechanical is wrapping up the HVAC system and
will begin testing the systems and plumbing will begin setting fixtures soon.
October
21, 2011 - Construction is proceeding as planned. Mother
Nature is cooperating with generally dry weather. Drywall is being installed as
nearly all windows have been installed and commissioned (tested). Painting is progressing
on all floors. The brick exterior is 80% complete. The bus parking is paved.
Improvements to
August
19, 2011 – Construction is
progressing on schedule. The building enclosure will soon be complete as the contractor
finishes the installation of windows, doors, and roof. The interior spaces have
been defined with the completion of interior stud walls. Electrical,
mechanical, and plumbing piping are now being installed in the walls. Soon wall
and floor finishes will begin.
July
21, 2011 – The extreme heat of this week has not slowed
progress on the facility. “I am pleased with the ongoing progress of the
District’s flood recovery project,” noted Dr. Dave Benson, Superintendent. “The
functions of the various departments it will house are beginning to take form
and the size and scope of the building are now clearly evident from both Ellis
and Edgewood Roads.”
July
7, 2011 – The contractor is beginning construction on
turn-lanes into the property on
June
14, 2011 – Progress continues
as this past week the exterior walls and roof framing was completed. Two of the
four geothermal wells have been completed as work continues on the last two.
Electrical, mechanical, and plumbing work continues on the interior as well as
metal stud wall framing. An air barrier is being installed on the exterior of
the building, followed by a spray-on insulation and brick. In the coming weeks
work on the loading dock, bus parking area, and a new
entrance on
April
20, 2011 – Members of the District’s Flood Recovery Core Team
and Board of Education recently toured the construction site to review progress
to date. Click the “Photos” link to see pictures from the April 15 tour.
March
23, 2011 – Check out the latest construction pictures by
clicking on the ‘photos’ link at the left.
March
3, 2011 – March is expected to bring a flurry of construction
activity on the site. At this point, the lower level concrete pours are
complete and structural steel is being set (and can be seen from the road).
Crews are working on water proofing and will begin the spray insulation process
by mid month.
February
1, 2011 – The District ELS Center has been recognized as one
of a community Sign of Progress. http://www.cr.k12.ia.us/news/Stories2010-2011/20110124A.html
January
7, 2011 – Earlier this week, Shive-Hattery
met with the contractor and sub-contractors to discuss exterior wall details
prior to any exterior wall construction. The discussions centered around responsibilities, constructability, sequencing, and
detail modifications. The cooperative discussions were very productive with an
end result of agreeable adjustments to the details which will maintain school
district goals and provide better and more efficient installation by the
contractors. This is a very unique opportunity to participate in these
discussions, one which will be repeated during construction.
December
29, 2010 – The Core Team appreciated a recent presentation
from Knutson Construction. The Project Manager explained the process used by
the firm to efficiently schedule the multiple and overlapping projects involved
in the facility’s construction.
December
3, 2010 – The pan deck is being poured today on the area
known as “D.” This includes the location for Buildings and Grounds,
November
17, 2010 – Members of the District’s Flood Recovery Core Team
recently toured the construction site to review progress to date. Click the
“Photos” link to see pictures from the Nov. 11 tour.
November
8, 2010- Most walls have now been poured in area “D”
(Buildings and Grounds,
November
1, 2010 – Progress is moving
along….A section of the wall and columns was recently poured with additional
walls being poured this week. Footings are also being put in. The staging area
will be complete by the end of this week. Grading is also in progress to
provide a smooth road for the variety of trucks that will be delivering project
materials to the site.
October
12, 2010 - The Board of
Education voted unanimously Oct. 11 to award the third and final bid package to
Knutson Construction Services of Iowa City.
The bid of $31.7 million was the lowest received
and less than the estimate projected by Shive-Hattery Inc.
Site
construction continues on the property. Recent dry weather has helped crews to
catch up on work that had been delayed by rain. The latest progress has
included the installation of a French drain and the geopier
grid. The building footprint is also now visible.
Oct.
1, 2010 - Site construction is now underway on the
Educational Leadership and
Site
construction began in August. Throughout the project, recycling and
sustainability will be an ongoing focus. Efforts have been made to retain as
many trees on property as possible. Those that couldn’t be saved were made into
mulch. As the Transportation building was taken down, the benches and overhead
doors were salvaged and the copper, fencing, concrete, asphalt, wiring,
conduits, light fixtures, steel, and aluminum were recycled.
Click on the links at the left for additional
information about the Educational Leadership and